Tuesday, October 23, 2012

CART PATH UPDATE:


Let the paving begin. Yesterday they finished the 8th hole and today they are working on 9. They are only working half a day tomorrow because of the Ray Jamison Pro-Am Tournament.  For the remainder of the week they will be working on 5-6 and 7.

Most of the staff is busy picking up leaves. We are also getting the bridge on four ready to be moved closer to the pond. This gets the path out of the middle of play and more off to the side. At the same time we are going to enlarge the green tee. It is way too small for the amount of play it receives.



Working in last Friday's rain. 

The official rain suit

Paving the 9th fairway cart path. 

 
Cart path will be moved to the right along the ponds so that it is less obtrusive.