Friday, December 16, 2011

BUNKER CONSTRUCTION NEARS COMPLETION

Not a moment too soon.  At last report this was the last week we could get sod before they stop harvesting.   Number five is complete.  Sand and sodding have been finished.  We are left with some scars, namely a haul road which will be leveled and seeded next spring.  Number 11 is complete except for adding sand to the bunker.  We hope to finish that next week. 

Good news,  The loan has been secured.  We can now start the process of installing the irrigation system.   It will take three weeks for the construction company to mobilize.  (May be even a little longer with the holidays)  Mother Nature holds the cards in respect to when they will start.  We will keep busy these next few months obtaining  permits for pond work and finalizing cart paths.  Now is the time to prepare so when the weather warms up we can hit the ground running.  I will certainly keep you posted  with weekly updates during the winter. 

The staff has been busy.  The drainage on 17 is completed.  We have started our winter maintenance on all the machines.  Frosty morning have allowed us to split some wood.  If you have a fireplace and want a few pieces please feel free to stop by the shop and pick up a few.  Stop and say hello,  we always have a pot of coffee on the burner. 

If I don't get a chance to update this,  Have a great Holiday and a Healthy and wonderful New Year. 

Five Fwy. bunkers completed

5 green right side bunkers completed

Number 11, we only need to add sand.  (the white bunker floor is from the liners) 

number 11 before the addition of the bunker.